[JP] Journalist Predicts Osaka Opening May Be Delayed Until the 2060s

Posted: 1. Nov 2026, 12:35
by maglev
[JP] Chuo Shinkansen Maglev: Journalist Predicts Osaka Opening May Be Delayed Until the 2060s

Source: Shueisha Online / Interview with journalist Hideki Kashida
Original title:
東京―大阪間のリニア開業は2060年? 工事遅延続々…「静岡悪者論」も今は昔、問題山積リニア開発の現在地
Date: August 8, 2025
Original language: Japanese
Web link: https://shueisha.online/articles/-/254744?page=1
Accessed: November 1, 2026

Journalist Hideki Kashida, who has investigated the Chuo Shinkansen maglev project for more than a decade, challenges the widespread assumption that Shizuoka Prefecture was primarily responsible for delaying the line. Based on construction progress he has examined since 2020, delays had already occurred in every other prefecture along the route, making the original 2027 opening target unrealistic from the outset.

Kashida criticizes JR Central for allegedly using Shizuoka's opposition to divert attention from delays elsewhere. Former Governor Heita Kawakatsu and Shizuoka residents faced widespread public criticism, although their opposition was rooted in environmental concerns.

Nearly 20 construction sections outside Shizuoka had reportedly not yet started. Kashida estimates that the Yamanashi side of the Southern Alps Tunnel may not be completed until the mid-2040s.

Environmental problems have emerged along the route. In Okute, Mizunami City, Gifu Prefecture, reduced or depleted water supplies were identified at 14 water sources, accompanied by ground subsidence. In Machida, Tokyo, oxygen-deficient air reportedly escaped from the ground in a residential garden.

Other concerns include severe noise near the Yamanashi maglev test track, residential displacement, groundwater depletion, inadequate disposal of excavated soil, and ongoing civil lawsuits seeking to halt construction.

Kashida also criticizes limited media coverage of these problems. He believes JR Central's advertising relationships with major media organizations and the scarcity of journalists continuously investigating the project have contributed to insufficient public scrutiny.

Financial viability raises further questions. Kashida refers to earlier statements by JR Central's management and the transport ministry indicating that the maglev project would struggle to become profitable. He considers the anticipated fare premium of approximately ¥700–1,000 over Tokaido Shinkansen Nozomi services insufficient to cover the costs.

Higher fares could turn maglev into a premium transport service primarily accessible to affluent passengers and international tourists. Kashida also points to the proposed Washington–Baltimore maglev project, where projected fares were reportedly up to eight times those of conventional rail services.

The most far-reaching concern is the opening schedule. Kashida estimates that the Tokyo–Osaka maglev connection may not become operational until the 2060s. He also doubts that a Shinagawa–Nagoya-only service would attract sufficient passengers to realize the project's intended benefits.

Water-resource impacts, construction difficulties, financial risks, and uncertain passenger demand therefore remain central to Kashida's criticism of the Chuo Shinkansen. His position emphasizes the need for closer scrutiny of the project's environmental consequences and long-term economic viability.

[JP] Chunichi Shimbun Estimates Maglev Shinagawa-Nagoya Opening at Earliest in the 2040s

Posted: 14. Nov 2026, 21:25
by latestnews
[JP] Chunichi Shimbun Estimates Maglev Shinagawa-Nagoya Opening at Earliest in the 2040s
Source: Chunichi Shimbun (chunichi.co.jp); reporting by Motomi Mizutani and Masahiro Tsukada
Original title:
リニア品川-名古屋開業、最短2040年代か 本紙試算、湧水対策など不確定要素
Translation of the original title: Maglev Shinagawa-Nagoya opening at the earliest in the 2040s, this newspaper's estimate finds; uncertain factors include spring-water countermeasures
Date: November 15, 2026, 5:10 a.m. (updated November 15, 2026, 5:10 a.m.)
Original language: Japanese
Web link:  https://www.chunichi.co.jp/article/1339597
Accessed: November 15, 2026

JR Central has indicated it will announce a new opening date for the Shinagawa-Nagoya section of the maglev Chuo Shinkansen within the year. The question is of great interest along the line and in surrounding regions because of its impact on station-area redevelopment and its economic ripple effects. Based on interviews with JR and tunnel engineering experts, the Chunichi Shimbun calculated the opening date and arrived at a result of the 2040s at the earliest.

The decisive factor is construction of the Southern Alps Tunnel Shizuoka section (8.9 km), which has not yet begun. JR Central President Shunsuke Niwa stated at a July press conference: "[Translated quote] What determines the opening date is the Shizuoka section (expected to be completed last)." The company originally assumed ten years from the start of construction in Shizuoka to the opening, but has indicated that this period will extend beyond the original assumption.