[JP] Maglev Opening not before the late 2040s?

Posted: 22. Nov 2026, 13:36
by maglev
[JP] Chuo Shinkansen Opening Could Slip into the 2040s – Tunnel Expert Estimates Completion by 2047

Source: TabiRis (旅行総合研究所タビリス)
Original title:
リニアはいつ開業できるのか。見通し公表延期、2040年代に?
Date: November 22, 2026, 08:51 JST; updated 08:56 JST
Original language: Japanese
Web link: https://news.jp/i/1497023346369266429
Accessed: November 22, 2026

The opening of the Chuo Shinkansen maglev line between Shinagawa and Nagoya remains uncertain. JR Central has postponed its planned announcement of a revised opening schedule from late 2026 to 2027 or later, citing the time required to reassess construction methods, schedules, and costs.

JR Central President Shunsuke Niwa explained on November 18: “[Translated quote] We are currently reviewing construction methods, construction periods, and construction costs, which are closely related to the construction periods, across all construction sections. However, this work is taking unexpectedly long, making it difficult to announce a new opening outlook by the end of the year.”

Shizuoka Construction Delayed

Although Shizuoka Prefecture approved construction in July 2026, work on the approximately 9-kilometer Southern Alps Tunnel section cannot begin before spring 2027. Lead contractor Taisei Corporation received a 120-day business suspension, from November 7, 2026, through March 6, 2027, following a maglev construction bid-rigging case.

If construction begins in 2027 and takes the previously assumed 10 years, opening would be possible in 2037 at the earliest. However, JR Central executive Hisao Sawada acknowledged that tunnel work in Yamanashi and Nagano has taken longer than expected and that Shizuoka construction could also exceed 10 years.

Construction Problems Along the Route

Other sections face delays. In Tokyo's approximately 9.2-kilometer Kita-Shinagawa tunnel section, excavation stopped in July 2026 after damage to the shield machine's gears and bearings. By November 16, tunneling had not resumed, with only about 734 meters excavated.

In Kawasaki, water and air erupted from the Katahira River bed near ongoing tunnel excavation on November 20. Work was suspended pending investigation; a causal connection with construction remains unconfirmed.

Groundwater depletion and land subsidence have interrupted construction in Mizunami, Gifu Prefecture. Meanwhile, completion of Nagoya's underground maglev station has slipped from 2027 to 2033 or later because of land acquisition difficulties and underground obstacles.

Tunnel Expert Suggests 2047 Completion

Osaka University Professor Emeritus Chikaosa Tanimoto analyzed the construction progress using publicly available information. While considering a roughly 10-year construction period in Shizuoka possible, he identified Kita-Shinagawa as the section most likely to determine overall completion.

Tanimoto said: “[Translated quote] I think that once the Kita-Shinagawa section is finished, all construction sections will be completed.”

He added: “[Translated quote] In the 2040s, by 2047, construction would be completed if conditions remain as they are now.”

Even if Shizuoka construction finishes around 2037, the line cannot open until all other critical sections are completed.

The postponement of JR Central's schedule announcement may indicate a substantially longer delay than previously anticipated. A commercial opening in the 2040s, potentially around 2047, is a scenario considered plausible by the author, not an official JR Central forecast.

[JP] JR Central's Indefinite Postponement of Its Maglev Opening Announcement Under Criticism

Posted: 25. Nov 2026, 12:13
by Miss Maglev
[JP] From "Shizuoka Alone Is to Blame" to "Problems in Every Section": JR Central's Indefinite Postponement of Its Maglev Opening Announcement Under Criticism

Source: President Online (president.jp), commentary by journalist Kazuya Kobayashi
Original title:
「静岡だけのせい」から一転「全工区の問題」に…リニア開業発表を「無期限延期」したJR東海の苦しすぎる言い訳
Translation of the original title: From "Shizuoka alone is to blame" to a reversal: "problems in every section" — JR Central's painful excuses after placing the maglev opening announcement on indefinite hold
Date: November 25, 2026, 4:00 p.m.
Original language: Japanese
Web link: https://president.jp/articles/-/122996
Accessed: November 25, 2026

JR Central had repeatedly stated that it would announce the Shinagawa-Nagoya opening date of the maglev Chuo Shinkansen once a prospect existed for starting work on the Southern Alps Tunnel's Shizuoka section. On November 18, however, President Shunsuke Niwa abandoned the planned announcement within the year, saying at a press conference: "[Translated quote] We are carrying out detailed reviews of construction methods, construction periods, and construction costs at all sections. Technical re-examinations have become necessary." He emphasized: "[Translated quote] That work is taking more time than expected." He characterized the fact that the general contractors for the Shizuoka section, including Taisei Corporation, have final convictions in the maglev bid-rigging case and can no longer have their contracts renewed as merely "one factor among several." The most serious problem is that, if this year is impossible, JR Central could not say even roughly when in the new year the announcement could be made.

Critically, the article notes, Niwa had previously stated clearly: "[Translated quote] What determines the opening date is the Shizuoka section (the last to be completed)." The company has not published a construction period for that section, but the completion of the most difficult section will in any case determine the opening date. In his book "The Maglev of 'Despair'" (Senmachi Shobo), Kobayashi predicts that the Shizuoka section will take about 30 years after breaking ground and that the Shinagawa-Nagoya opening will come around 2060. [Note: The causal links and information asserted here may not be accurate, but they reflect the author's view.]JR Central chose the Southern Alps route on the basis of desk calculations prioritizing economic rationality, claiming its superiority over a detour route through Nagano in all respects; the writer suggests the company may now, through this review, be belatedly recognizing how difficult the Southern Alps crossing really is.

On December 14, 2023, JR Central applied for a revision approving a total construction cost raised from 5,523.5 billion yen to 7,047.8 billion yen, and changed the opening date from "2027" to "2027 or later." On July 18 this year, JR Central concluded an agreement with Shizuoka Prefecture based on the start of the Shizuoka section work, and on July 24 Niwa told the land and transport minister that the opening date would be announced within the year. This commitment then softened: at an October 28 press conference he spoke only of a plan "under consideration" for announcement within the year, and on October 23 the final convictions in the bid-rigging case and the resulting 120-day business suspension order on Taisei Corporation ended all contract discussions. Niwa called the suspension period itself insignificant compared with the total construction period, but even after it expires on March 7 next year, negotiations with Taisei are expected to be difficult.

On November 4, Kyodo News reported, as an exclusive, that the total construction cost study was moving toward an increase beyond 11 trillion yen, possibly with an announcement within the year and an opening date expressed not as a specific year but as a range. At a November 12 press conference, Niwa denied this report and repeated that the announcement within the year remained unchanged — in effect branding Kyodo's exclusive a false report. JR Central had only just announced last year that it provisionally placed the opening in 2035 for convenience and raised the total cost from 7,047.8 billion yen to 11 trillion yen, including a 1-trillion-yen reserve for further price-driven rises. By citing the review of all sections as the reason for abandoning the November announcement, Kobayashi argues, Niwa effectively suggested the 1-trillion-yen reserve is insufficient and the total may exceed 11 trillion yen, making the 2035 placeholder far too optimistic.

Suspiciously, the Chunichi Shimbun reported on November 15 that, estimating the Shizuoka section work at 14 to 16 years based on the progress of the Yamanashi and Nagano sections, the opening would come in 2043 to 2045 at the earliest. To that estimate, JR Central gave its standard comment that the outlook would be presented within the year — yet two days later, on November 17, Niwa reportedly reported to the land and transport minister that the announcement within the year was abandoned. In the writer's reading, the company maintained the "within the year" posture toward the media while deciding internally to drop it. As for why the abandonment was announced on November 18 rather than at year's end, Kyodo's report on the cost review suggests JR Central may intend to announce a cost increase in December, before entering contract-renewal talks with Taisei after March.

The change of justification draws particular criticism: after former Shizuoka Governor Heita Kawakatsu opposed the Shizuoka section in October 2017 until his resignation in May 2024 over remarks unrelated to the maglev, JR Central was occupied with Shizuoka for seven years, while nearly all other sections had already begun construction before that date, targeting completion by 2026 for a 2027 opening. Claiming now that all sections' schedules and costs need topping-up review strikes the writer as inexplicable, and many will ask what all the earlier statements were for. Takashi Yamane, former chairman of Taisei Corporation, pointed to JR Central's limited experience planning Shinkansen lines and said: "[Translated quote] Various blemishes have appeared, and completion is becoming harder and harder. People used to say enthusiastically, 'Once the maglev is completed to Nagoya, next comes Osaka,' but that talk has suddenly gone quiet, and now even whether the line will ever break through to Nagoya is in doubt." (Bungeishunju, February 2026 issue)

Kobayashi concludes that JR Central itself knows best that the maglev project's calculations no longer add up. For now, however, withdrawal is not an option: the government, which extended 3 trillion yen in special loans, the municipalities along the line with high expectations, and above all the residents forced to relocate to provide the land would not forgive it.