[JP] Maglev Opening not before the late 2040s?
Posted: 22. Nov 2026, 13:36
[JP] Chuo Shinkansen Opening Could Slip into the 2040s – Tunnel Expert Estimates Completion by 2047
Source: TabiRis (旅行総合研究所タビリス)
Original title:
リニアはいつ開業できるのか。見通し公表延期、2040年代に?
Date: November 22, 2026, 08:51 JST; updated 08:56 JST
Original language: Japanese
Web link: https://news.jp/i/1497023346369266429
Accessed: November 22, 2026
The opening of the Chuo Shinkansen maglev line between Shinagawa and Nagoya remains uncertain. JR Central has postponed its planned announcement of a revised opening schedule from late 2026 to 2027 or later, citing the time required to reassess construction methods, schedules, and costs.
JR Central President Shunsuke Niwa explained on November 18: “[Translated quote] We are currently reviewing construction methods, construction periods, and construction costs, which are closely related to the construction periods, across all construction sections. However, this work is taking unexpectedly long, making it difficult to announce a new opening outlook by the end of the year.”
Shizuoka Construction Delayed
Although Shizuoka Prefecture approved construction in July 2026, work on the approximately 9-kilometer Southern Alps Tunnel section cannot begin before spring 2027. Lead contractor Taisei Corporation received a 120-day business suspension, from November 7, 2026, through March 6, 2027, following a maglev construction bid-rigging case.
If construction begins in 2027 and takes the previously assumed 10 years, opening would be possible in 2037 at the earliest. However, JR Central executive Hisao Sawada acknowledged that tunnel work in Yamanashi and Nagano has taken longer than expected and that Shizuoka construction could also exceed 10 years.
Construction Problems Along the Route
Other sections face delays. In Tokyo's approximately 9.2-kilometer Kita-Shinagawa tunnel section, excavation stopped in July 2026 after damage to the shield machine's gears and bearings. By November 16, tunneling had not resumed, with only about 734 meters excavated.
In Kawasaki, water and air erupted from the Katahira River bed near ongoing tunnel excavation on November 20. Work was suspended pending investigation; a causal connection with construction remains unconfirmed.
Groundwater depletion and land subsidence have interrupted construction in Mizunami, Gifu Prefecture. Meanwhile, completion of Nagoya's underground maglev station has slipped from 2027 to 2033 or later because of land acquisition difficulties and underground obstacles.
Tunnel Expert Suggests 2047 Completion
Osaka University Professor Emeritus Chikaosa Tanimoto analyzed the construction progress using publicly available information. While considering a roughly 10-year construction period in Shizuoka possible, he identified Kita-Shinagawa as the section most likely to determine overall completion.
Tanimoto said: “[Translated quote] I think that once the Kita-Shinagawa section is finished, all construction sections will be completed.”
He added: “[Translated quote] In the 2040s, by 2047, construction would be completed if conditions remain as they are now.”
Even if Shizuoka construction finishes around 2037, the line cannot open until all other critical sections are completed.
The postponement of JR Central's schedule announcement may indicate a substantially longer delay than previously anticipated. A commercial opening in the 2040s, potentially around 2047, is a scenario considered plausible by the author, not an official JR Central forecast.
Source: TabiRis (旅行総合研究所タビリス)
Original title:
リニアはいつ開業できるのか。見通し公表延期、2040年代に?
Date: November 22, 2026, 08:51 JST; updated 08:56 JST
Original language: Japanese
Web link: https://news.jp/i/1497023346369266429
Accessed: November 22, 2026
The opening of the Chuo Shinkansen maglev line between Shinagawa and Nagoya remains uncertain. JR Central has postponed its planned announcement of a revised opening schedule from late 2026 to 2027 or later, citing the time required to reassess construction methods, schedules, and costs.
JR Central President Shunsuke Niwa explained on November 18: “[Translated quote] We are currently reviewing construction methods, construction periods, and construction costs, which are closely related to the construction periods, across all construction sections. However, this work is taking unexpectedly long, making it difficult to announce a new opening outlook by the end of the year.”
Shizuoka Construction Delayed
Although Shizuoka Prefecture approved construction in July 2026, work on the approximately 9-kilometer Southern Alps Tunnel section cannot begin before spring 2027. Lead contractor Taisei Corporation received a 120-day business suspension, from November 7, 2026, through March 6, 2027, following a maglev construction bid-rigging case.
If construction begins in 2027 and takes the previously assumed 10 years, opening would be possible in 2037 at the earliest. However, JR Central executive Hisao Sawada acknowledged that tunnel work in Yamanashi and Nagano has taken longer than expected and that Shizuoka construction could also exceed 10 years.
Construction Problems Along the Route
Other sections face delays. In Tokyo's approximately 9.2-kilometer Kita-Shinagawa tunnel section, excavation stopped in July 2026 after damage to the shield machine's gears and bearings. By November 16, tunneling had not resumed, with only about 734 meters excavated.
In Kawasaki, water and air erupted from the Katahira River bed near ongoing tunnel excavation on November 20. Work was suspended pending investigation; a causal connection with construction remains unconfirmed.
Groundwater depletion and land subsidence have interrupted construction in Mizunami, Gifu Prefecture. Meanwhile, completion of Nagoya's underground maglev station has slipped from 2027 to 2033 or later because of land acquisition difficulties and underground obstacles.
Tunnel Expert Suggests 2047 Completion
Osaka University Professor Emeritus Chikaosa Tanimoto analyzed the construction progress using publicly available information. While considering a roughly 10-year construction period in Shizuoka possible, he identified Kita-Shinagawa as the section most likely to determine overall completion.
Tanimoto said: “[Translated quote] I think that once the Kita-Shinagawa section is finished, all construction sections will be completed.”
He added: “[Translated quote] In the 2040s, by 2047, construction would be completed if conditions remain as they are now.”
Even if Shizuoka construction finishes around 2037, the line cannot open until all other critical sections are completed.
The postponement of JR Central's schedule announcement may indicate a substantially longer delay than previously anticipated. A commercial opening in the 2040s, potentially around 2047, is a scenario considered plausible by the author, not an official JR Central forecast.