[JP] JR Central Expected to Postpone Announcement of Maglev Opening Date Until 2027
Posted: 17. Nov 2026, 22:31
[JP] JR Central Expected to Postpone Announcement of Revised Chuo Shinkansen Opening Date Until 2027
Source: Asahi Shimbun
Original title:
リニア中央新幹線の開業時期 JR東海、年内の見通し公表を断念へ
Date: November 18, 2026, 00:38 JST
Original language: Japanese
Web link: https://www.asahi.com/articles/ASVCK544 ... A037M.html
Accessed: November 18, 2026 (JST)
JR Central is expected to abandon its plan to announce a revised opening schedule for the Chuo Shinkansen maglev line before the end of 2026. Company President Shunsuke Niwa is expected to explain the decision at a press conference in Nagoya on November 18.
At a press conference on November 12, Niwa had still maintained: “[Translated quote] We are proceeding with our review with the intention of presenting an outlook by the end of the year.”
Several construction difficulties have complicated the schedule. JR Central has already abandoned plans to begin construction in the Shizuoka section before the end of 2026 after Taisei Corporation, the major contractor responsible for the section, received a business suspension order.
Additional problems include damage to components of a tunnel boring machine (shield machine) at a construction site in Tokyo's Shinagawa Ward and delays in construction of the new underground maglev station at Nagoya.
These developments appear to require a further reassessment before JR Central can present a reliable opening schedule.
The original construction plan, approved by Japan's Ministry of Land, Infrastructure, Transport and Tourism in 2014, targeted an opening in 2027. That target was subsequently abandoned following construction delays in the Shizuoka section caused by environmental disputes.
No revised opening date has yet been announced.
Source: Asahi Shimbun
Original title:
リニア中央新幹線の開業時期 JR東海、年内の見通し公表を断念へ
Date: November 18, 2026, 00:38 JST
Original language: Japanese
Web link: https://www.asahi.com/articles/ASVCK544 ... A037M.html
Accessed: November 18, 2026 (JST)
JR Central is expected to abandon its plan to announce a revised opening schedule for the Chuo Shinkansen maglev line before the end of 2026. Company President Shunsuke Niwa is expected to explain the decision at a press conference in Nagoya on November 18.
At a press conference on November 12, Niwa had still maintained: “[Translated quote] We are proceeding with our review with the intention of presenting an outlook by the end of the year.”
Several construction difficulties have complicated the schedule. JR Central has already abandoned plans to begin construction in the Shizuoka section before the end of 2026 after Taisei Corporation, the major contractor responsible for the section, received a business suspension order.
Additional problems include damage to components of a tunnel boring machine (shield machine) at a construction site in Tokyo's Shinagawa Ward and delays in construction of the new underground maglev station at Nagoya.
These developments appear to require a further reassessment before JR Central can present a reliable opening schedule.
The original construction plan, approved by Japan's Ministry of Land, Infrastructure, Transport and Tourism in 2014, targeted an opening in 2027. That target was subsequently abandoned following construction delays in the Shizuoka section caused by environmental disputes.
No revised opening date has yet been announced.