[JP] JR Central Expected to Postpone Announcement of Maglev Opening Date Until 2027

User avatar
latestnews
Posts: 577
Joined: 1. Oct 2021, 13:44

[JP] JR Central Expected to Postpone Announcement of Maglev Opening Date Until 2027

Unread post by latestnews »

[JP] JR Central Expected to Postpone Announcement of Revised Chuo Shinkansen Opening Date Until 2027

Source: Asahi Shimbun
Original title:
リニア中央新幹線の開業時期 JR東海、年内の見通し公表を断念へ
Date: November 18, 2026, 00:38 JST
Original language: Japanese
Web link: https://www.asahi.com/articles/ASVCK544 ... A037M.html
Accessed: November 18, 2026 (JST)

JR Central is expected to abandon its plan to announce a revised opening schedule for the Chuo Shinkansen maglev line before the end of 2026. Company President Shunsuke Niwa is expected to explain the decision at a press conference in Nagoya on November 18.

At a press conference on November 12, Niwa had still maintained: “[Translated quote] We are proceeding with our review with the intention of presenting an outlook by the end of the year.”

Several construction difficulties have complicated the schedule. JR Central has already abandoned plans to begin construction in the Shizuoka section before the end of 2026 after Taisei Corporation, the major contractor responsible for the section, received a business suspension order.

Additional problems include damage to components of a tunnel boring machine (shield machine) at a construction site in Tokyo's Shinagawa Ward and delays in construction of the new underground maglev station at Nagoya.

These developments appear to require a further reassessment before JR Central can present a reliable opening schedule.

The original construction plan, approved by Japan's Ministry of Land, Infrastructure, Transport and Tourism in 2014, targeted an opening in 2027. That target was subsequently abandoned following construction delays in the Shizuoka section caused by environmental disputes.

No revised opening date has yet been announced.

User avatar
latestnews
Posts: 577
Joined: 1. Oct 2021, 13:44

Re: [JP] JR Central Expected to Postpone Announcement of Maglev Opening Date Until 2027

Unread post by latestnews »

[JP] JR Central Abandons Plan to Announce Revised Maglev Opening Date in 2026

Source: Chunichi Shimbun
Original title:
リニア開業時期、年内示せず JR東海が公表断念
Date: November 18, 2026, 01:16 JST
Original language: Japanese
Web link: https://www.chunichi.co.jp/article/1340930
Accessed: November 18, 2026

JR Central has informed Japan's Ministry of Land, Infrastructure, Transport and Tourism that it has abandoned its plan to announce a revised opening date for the Shinagawa–Nagoya section of the Chuo Shinkansen maglev line before the end of 2026. Company President Shunsuke Niwa is expected to explain the decision at a press conference on November 18.

In July, Niwa had informed then-Minister of Land, Infrastructure, Transport and Tourism Yasushi Kaneko of his intention to present an opening outlook before the end of the year.

JR Central had planned to determine the opening date based on the construction period required for the Shizuoka section of the Southern Alps Tunnel, which remains unstarted and is expected to be the last section completed.

Following the fulfillment of the conditions for starting construction in Shizuoka in July, JR Central continued negotiations with Taisei Corporation, the lead contractor in the joint venture responsible for the section, over the construction schedule and contract costs. These discussions appear to have encountered difficulties.

User avatar
latestnews
Posts: 577
Joined: 1. Oct 2021, 13:44

[JP] Maglev Opening in the 2030s Increasingly Unlikely

Unread post by latestnews »

[JP] JR Central Unable to Forecast Shizuoka Construction Start – Maglev Opening in the 2030s Increasingly Unlikely

Source: Nikkei
Original title:
JR東海、リニア「静岡着工時期の見通したたず」 30年代開業は難しく
Date: November 18, 2026, 17:33 JST
Original language: Japanese
Web link: https://www.nikkei.com/article/DGXZQOFD ... 1C2000000/
Accessed: November 19, 2026

JR Central announced on November 18 that it will postpone the announcement of its revised opening schedule for the Shinagawa–Nagoya section of the Chuo Shinkansen maglev line until 2027 or later, abandoning its previous commitment to publish an outlook by the end of 2026.

Construction delays have prolonged the reassessment of construction schedules and costs. An opening in the late 2030s, previously considered possible, may be delayed further.

At a press conference in Nagoya, JR Central President Shunsuke Niwa said: “[Translated quote] We would like to present an outlook as early as possible.”

User avatar
latestnews
Posts: 577
Joined: 1. Oct 2021, 13:44

Re: [JP] JR Central Expected to Postpone Announcement of Maglev Opening Date Until 2027

Unread post by latestnews »

[JP] JR Central Postpones Maglev Opening Forecast and Considers Revising Construction Methods to Reduce Costs

Source: Nikkei
Original title:
JR東海、リニア開業時期の年内公表断念 コスト減へ工法見直しも
Date: November 18, 2026, 09:29 JST
Original language: Japanese
Web link: https://www.nikkei.com/article/DGXZQOFD ... 1C2000000/
Accessed: November 19, 2026

JR Central has postponed the announcement of its projected opening date for the Shinagawa–Nagoya section of the Chuo Shinkansen maglev line until 2027 or later.

Anticipated construction difficulties in the Shizuoka section of the Southern Alps Tunnel have reduced the urgency of completing other construction sections. JR Central is therefore considering cost-cutting measures, including revisions to construction methods and adjustments to construction schedules.

User avatar
latestnews
Posts: 577
Joined: 1. Oct 2021, 13:44

[JP] Nagoya Chamber of Commerce Expresses Disappointment over Postponed Maglev Opening Forecast

Unread post by latestnews »

[JP] Nagoya Chamber of Commerce Expresses Disappointment over Postponed Maglev Opening Forecast

Source: Chubu Keizai Shimbun (中部経済新聞)
Original title:
嶋尾会頭「非常に残念」 名商 リニア時期の提示延期で
Date: November 26, 2026
Original language: Japanese
Web link: https://www.chukei-news.co.jp/news/2026 ... 260201_04/
Accessed: November 26, 2026

Tadashi Shimao, chairman of the Nagoya Chamber of Commerce and Industry, expressed disappointment on November 25 over JR Central's decision to postpone its Shinagawa–Nagoya maglev opening forecast until 2027 or later.

“[Translated quote] This is extremely disappointing. I would like the opening date to be announced as soon as possible.”

Shimao emphasized the implications for urban development and private investment along the route:

“[Translated quote] If an opening date is announced, construction of hotels and other facilities will accelerate as schedules are planned backward from that date. Many stakeholders are eager to know the opening date.”

He also called for continued disclosure of information whenever changes occur during the project's lengthy implementation.

User avatar
latestnews
Posts: 577
Joined: 1. Oct 2021, 13:44

][JP] Shizuoka Governor and Transport Minister Call for Early Announcement of Revised Maglev Opening Forecast

Unread post by latestnews »

[JP] Shizuoka Governor and Transport Minister Call for Early Announcement of Revised Maglev Opening Forecast

Source: Shizuoka Asahi Television (静岡朝日テレビ), published on News.jp
Original title:
【リニア】静岡・鈴木知事「できるだけ早く開業時期のめどを」 井林国交大臣も「予見性確保のためにも1日も早く見通し示して」
Date: November 26, 2026, 19:11 JST
Original language: Japanese
Web link: https://news.jp/i/1498627699337003758?c ... 9549373591
Accessed: November 26, 2026

Shizuoka Governor Yasutomo Suzuki called for an early announcement of the revised Chuo Shinkansen maglev opening forecast following JR Central's decision not to release it before the end of 2026.

Suzuki intends to use the revised forecast as a basis for further coordination with JR Central and municipalities along the Tokaido corridor.

JR Central President Shunsuke Niwa announced on November 18 that reviewing construction methods, schedules, and associated costs across all construction sections was taking longer than expected.

On November 20, Transport Minister Tatsunori Ibayashi emphasized the importance of planning certainty:

“[Translated quote] We recognize that it is important to present an outlook as soon as possible to ensure predictability for regional stakeholders engaged in station-area development and urban planning.”

Governor Suzuki also called for a thorough assessment of rising construction costs and further consultations among the parties involved before a specific opening forecast is announced.